The process of assembling lithium battery cells into a group is called pack, which can be a single battery or a series parallel battery module.
Pack consists of battery pack, bus bar, soft connection, protection board, outer package, output (including connector), highland barley paper, plastic cell holder and other auxiliary materials.
Features of Pack
1. Pack of battery pack requires high consistency of battery (capacity, internal resistance, voltage, discharge curve, life).
2. The cycle life of battery pack is lower than that of single battery.
3. Using under limited conditions (including charging, discharging current, charging mode, temperature, etc.).
4. The voltage and capacity of lithium battery pack have been greatly improved after forming, so it must be protected and monitored for charge balance, temperature, voltage and overcurrent.
5. The battery pack must meet the voltage and capacity requirements required by the design.
Pack Method
1. Series Parallel Composition
The battery is composed of single battery through parallel series connection.
When the capacity is increased in parallel, the voltage does not change.
After the series connection, the voltage multiplies and the capacity does not change.
For example, 3.6v/10ah battery is composed of a single N18650 / 2Ah through 5.
Parallel before series: due to the difference of internal resistance and uneven heat dissipation, parallel will affect the cycle life of battery.
However, the failure of a single battery automatically exits, in addition to capacity reduction, which does not affect the use of parallel, parallel technology is relatively strict.
When a unit battery in parallel is short circuited, the current of parallel circuit is very large, which is usually avoided by fuse protection technology.
Series Before Parallel
According to the capacity of the whole battery, series connection is carried out first, for example, the capacity of the whole battery is 1 / 3, and then parallel connection is carried out to reduce the failure probability of large capacity battery.
2. Requirements for Electric Core
Select corresponding electric core according to the design requirements.
The parallel and series batteries shall have the same type and model, and the difference in capacity, internal resistance and voltage value shall not be greater than 2%.
In general, the capacity loss of the battery is 2% - 5% when it is combined in series and parallel.
The more the number of batteries, the more the capacity loss.
No matter it is a soft packed battery or a cylindrical battery, it needs to be combined in multiple strings. If the consistency is poor, the battery capacity will be affected.
The battery with the lowest capacity in a group determines the capacity of the whole group of batteries.
High current discharge performance is required.
The starting current of the motor is three times of the normal working current, and the power performance of the motor can be improved only when the large current is discharged.
Good heat dissipation of battery is required.
The number of batteries is large, and the temperature rise of the batteries inside the battery box is not easy to disperse, resulting in uneven temperature and different discharge characteristics among the batteries, resulting in long-term degradation of battery performance. High level of production technology.
Others
1. Cylindrical battery pack assembly line machine is suitable for all kinds of cylindrical battery pack makingaccording to customer's requirement.
2. Machine can be chosen according to customer's cell productivity.
3. Economic and high-efficiency.
Battery Cell, Module and Pack, What's the Diffenence?
Detailed Flowchart for Lithium Battery Pack Assembling
Detailed Steps to be Followed in Making Battery Pack
1. Cell Testing
Testing is done to establish the cell parameters i.e. voltage, capacity, cycle life ect.
2. BMS Testing
This Step checks whether the battery protection circuit functional indicators fall within the paramenter range.
3. Pasting Insulating Paper on the Positive Pole
Small insulating paper is pasted on the poles of cells to prevent a short circuit.
4. Battery Sorting
Batteryies are sorted according to their voltage and internal resistance.
The same voltage and internal resistance value battery are kept togather , so that consistency and stability of the whole battery pack is assured during its life.
5. Putting the Cells in Brackets and Moulds
Cells are given a supporting structure to weld the together.
Nickel strips are also placed in the moulds to weld cells together.
6. CCD Testing
Before welding the cells, CCD testing is done to ensure that the positive and negative poles of the battery are above and below to prevent short circuiting.
7. Welding Cells
Welding of multiple cells provides a higher capacity battery.
A company uses any one of the welding techniques--spot welding, laser welding ect.
8. Pasting Insulation Paper and Pre-treatment of Battery Poles
Insulating paper is pasted on the battery pack to prevent the aging of PVC and so that chances of short circuit are reduced.
Pre-treatment of the battery poles is required to weld BMS easily.
9. Connecting BMS
Battery Management System is connected to the battery pack, so that it can be operated in the desired range.
10. Battery Pack Testing
A finished battery pack is tested to determine the charge and discharge voltage, charge and discharge current and total internal resistance.
11. Battery Pack Aging Test
A battery pack is charged and discharged several times and its capacity is recorded at each charge and discharge to detect the battery charge protection and discharge protection.
Main Stations
Station
Job
Other Special Requirement
Cell Grading
Evaluate classify cells according to different voltage values
Inserting Cell
Insert cell into module's housing
Insert correctly into positions, don't allow positive and negative of cell connecting
Holder Assembly and Bolting
Module's top holder assembly. Screw fastener
Vison Checking
Checking module's polarity
Camera checking
Welding
Welding metal's sheet and connect module's electrode
Provide guiding JIG for correct welding procedure
Shipping Timeframes: All orders are processed within 2-5 business days (excluding weekends and holidays). After your order has been processed, the estimated delivery time is before 13 Apr, 2025, depending on customs, Please note that due to high demand, some items may experience longer shipping times, which will be communicated at order confirmation email.
Order Processing Time: Please allow 2-5 business days for us to process your order before it is shipped . Orders placed after 16:00 on Fridays, or during weekends and public holidays, will begin processing on the next business day. Processing times may be extended during peak seasons or sales events.
Manufacturing Time: Some products needs manufacturing time, the manufacturing process will take approximately 10-30 business days depending on the product. This timeframe may vary depending on the complexity of the product and current demand. but this will be communicated with you during order confirmation.
Returns and Exchanges: We offer a 30-day return policy for most items. If you are not completely satisfied with your purchase, you may return it within 30 days of receipt for a refund or exchange. Items must be unused, in their original packaging, and accompanied by proof of purchase. Return shipping costs are the responsibility of the customer, unless the item was damaged or defective upon arrival.
0
0 Overall Rating
5
0%
0
4
0%
0
3
0%
0
2
0%
0
1
0%
0
Review this product
For you to write a review, you need to login first
At Afrimart, we strive to process all orders promptly. Once the payment has been successfully cleared into our account, your order will be processed within 2 to 5 business days. Please note that this processing time excludes weekends and public holidays.
Following the processing of your order, the estimated delivery lead time ranges between 35 to 60 days. However, please be aware that this timeframe is subject to variations due to potential delays in shipping and customs clearance. While we aim to adhere to the original delivery schedule, unforeseen circumstances may occasionally extend the delivery window beyond the anticipated 35 to 60 days.
In the event of high demand or other factors leading to longer shipping times for certain items, we will communicate any expected delays during the initial order confirmation. We appreciate your understanding and patience as we work to ensure your order arrives as swiftly as possible.