Corn flour, rice flour, Chicken, meat, bone, water etc
4
Flow chart
Grinder→Mixer →Bucket Conveyor→ Twin Screw Extruder with Pre-conditioner→Vibrating Sifter→HighPressure Air Conveyor → Multi-layer Dryer → Hoister → Oil-sprayer→ Length Single Roller FlavoringSystem→Hoister→ Cooling Machine→ High Pressure Air Conveyor→ Packing Machine
5
Factory Requirement
a. Workshop: L-50M / W-3M / H-7.5M (Straight line size, it can be adjusted according to your workshop)
b. Operator: 3-5 person
c .Three-phase voltage: 380V/50Hz
6
Installation power
280kw
Machine List:
No.
Name
Model
Qty
Power (kw)
Dimension(mm)
1
Grinder
FS-600
1Set
37kw
800*800*1400
2
Mixer Machine
BFJ-JZQ-350
1Set
11kw
2800*1200*2000
3
Bucket Conveyor
DT-II
1Set
1.5 kw
1500*700*7350
4
Twin Screw Extruder with Pre-conditioner
TSE95-P
1Set
115 kw
5200*1100*6000
5
Vibrating Sifter
ZDS-II
1Set
0.45 kw
1500*750*740
6
Cooling Machine
LQSS-I
1Set
1.07kw
5300*690*1470
7
High Pressure Air Conveyor
FSJ-II
1Set
3kw
3500*600*3550
8
Steam dryer
KX-5-11
1Set
50kw
12500x1700x3500
9
Hoister with flavoring part
ZTTW-I
1Set
1.12kw
1950*700*1460
10
Oil-sprayer
PYJ-I
1Set
4.37kw
940*630*750
11
Length Single Roller Flavoring System
DGT-II
1Set
1.5kw
4000*870*1780
12
Hoister
TSJ-II
1Set
0.37kw
2050*700*2350
13
Cooling Machine
LQJ-5-5
1Set
22.65kw
5200*1200*2000
14
High Pressure Air Conveyor
FSJ-III
1Set
3kw
3500*600*3550
15
Packing Machine+Air Compressor
GQ-25K
1Set
1.5kw+2.2kw
2800*900*2500
Spare Parts Included:
Shipping Timeframes: All orders are processed within 2-5 business days (excluding weekends and holidays). After your order has been processed, the estimated delivery time is before 23 Jun, 2025, depending on customs, Please note that due to high demand, some items may experience longer shipping times, which will be communicated at order confirmation email.
Order Processing Time: Please allow 2-5 business days for us to process your order before it is shipped . Orders placed after 16:00 on Fridays, or during weekends and public holidays, will begin processing on the next business day. Processing times may be extended during peak seasons or sales events.
Manufacturing Time: Some products needs manufacturing time, the manufacturing process will take approximately 10-30 business days depending on the product. This timeframe may vary depending on the complexity of the product and current demand. but this will be communicated with you during order confirmation.
Returns and Exchanges: We offer a 30-day return policy for most items. If you are not completely satisfied with your purchase, you may return it within 30 days of receipt for a refund or exchange. Items must be unused, in their original packaging, and accompanied by proof of purchase. Return shipping costs are the responsibility of the customer, unless the item was damaged or defective upon arrival.
0
0 Overall Rating
5
0%
0
4
0%
0
3
0%
0
2
0%
0
1
0%
0
Review this product
For you to write a review, you need to login first
At Afrimart, we strive to process all orders promptly. Once the payment has been successfully cleared into our account, your order will be processed within 2 to 5 business days. Please note that this processing time excludes weekends and public holidays.
Following the processing of your order, the estimated delivery lead time ranges between 35 to 60 days. However, please be aware that this timeframe is subject to variations due to potential delays in shipping and customs clearance. While we aim to adhere to the original delivery schedule, unforeseen circumstances may occasionally extend the delivery window beyond the anticipated 35 to 60 days.
In the event of high demand or other factors leading to longer shipping times for certain items, we will communicate any expected delays during the initial order confirmation. We appreciate your understanding and patience as we work to ensure your order arrives as swiftly as possible.